D CV-20-03: DEMIX
emailShare
linkPermalink
Number:
CV-20-03
Title:
DEMIX
Status:
Open
Creation Year:
2020
Completion Date:
2024 Q1 (2 days remaining)
Description:

Intecomparison of publicly-available DEM

Link to GEO Work Programme:
GEO BON; GEOGLAM; GFOI
External Reference:
Responsible Users:
Peter Strobl, Riza Singh
Responsible CEOS Entities:
Contributing Agencies:
ESA, EC, USGS, tbc: NASA, JAXA, CNES, DLR,
Progress Reports:
2020-09-04 21:09:32 UTC
on track
Peter Strobl | 2022-09-06 13:41:08 UTC

The activity has been extended due to continuous improvements of the methods and very diverse results which required additional attention. The final report in form of a peer-reviewed paper is now close to submission and results are going to be presented at WGCV 54 in Tokyo. The current phase of DEMIX will be concluded by the end of 2022, but there are already plans for follow on activities which will be discussed at a dedicated TMSG/DEMIX workshop in spring 2023.

Marie-Claire Greening | 2023-02-12 18:27:10 UTC

Work is mostly finished, a second peer-reviewed article is close to submission. Further results will be presented in July at a dedicated workshop at geomorphometry23: https://geomorphometry.org/geomorphometry-2023/ and gradually be made available also through the Cal/Val portal

Peter Strobl | 2023-10-09 11:03:14 UTC

DEMIX Workshop and TMSG Plenary took place in Iasi, RO on Huly 12/13 2023. A summary will be provided at the next WGCV meeting.

Excecutive Support - Evenflow | 2024-02-26 15:10:22 UTC

Peer reviwed publication with final DEMIX results accepted at TGRS, comprehensive report about DEMIX in final stage of review as JRC technical report.

Comments:
| 2020-09-04 21:09:32 UTC
There are some delays related to COVID-19 but still on track to complete by deadline.
Peter Strobl | 2022-09-06 13:41:58 UTC

The current phase of DEMIX will be concluded by the end of 2022, but there are already plans for follow on activities which will be discussed at a dedicated TMSG/DEMIX workshop in spring 2023.

Peter Strobl | 2023-10-09 11:05:04 UTC

A major publication covering DEMIX is still under perr-review and the final report is close to completion.

Peter Strobl | 2023-11-10 17:39:10 UTC

Review is unfortunately dragging on, still hope to conclude this year.

Actions:
Created:
2020-09-04 21:09:32 UTC
Last Updated: