arrow_backBack

View Deliverable


D COV-18-01: COVERAGE Phase C system
emailShare
linkPermalink
Number:
COV-18-01
Title:
COVERAGE Phase C system
Status:
Open
Creation Year:
2018
Completion Date:
2022 Q3 (434 days remaining)
Description:

Implementation of fully featured COVERAGE system in support of designated GEO application

Link to GEO Work Programme:
External Reference:
Responsible Users:
Vardis Tsontos
Responsible CEOS Entities:
COVERAGE
Contributing Agencies:

Progress Reports:
V. Tsontos | 2019-09-12 21:34:01 UTC

The COVERAGE Phase-C work will be initiated upon completion of the Phase-B activity (Q4 2020).  Phase-C is a one year activity that will now run over the period Q1-Q4 2021.

Comments:
V. Tsontos | 2019-09-12 21:36:30 UTC

The completion date of COV-5 will need to be updated from 2021 Q1 to 2021 Q4 as mentioned in the latest progress report above.

V. Tsontos | 2020-05-28 22:31:21 UTC

As mentioned in my prior comment a while back, the completion date of COV-5 will need to be updated from 2021 Q1 to 2021 Q4 by someone who has priviledges to modify dates.

This activity is expected to begin Q1 2011 and run for a year

V. Tsontos | 2021-01-29 20:39:18 UTC

The COVERAGE Phase-C activity is expected to begin towards the end of Q1-2021.  It is now planned as an 18-month in duration activity with an anticipated completion date in Q3-2022.

Actions:
Created:
2019-09-07 03:10:24 UTC
Last Updated:
2021-02-17 15:28:00 UTC