D COV-03: COVERAGE Project Implementation Plan
Title:
COVERAGE Project Implementation Plan
Link to GEO Work Programme:
Responsible CEOS Entities:
Relevant Sustainable Development Goal (SDG):
Progress Reports:
2019-07-21 10:29:56 UTC
Oct 06, 2017:
- Phase-A COVERAGE project approved and supported by NASA
- Project expected to kicks-off October 2017 (Phase A)
- Detailed COVERAGE project implementation plan (Phases B-D) to be developed during Phase A
- COVERAGE workshop proposal under development in collaboration with Sargasso Sea Commission (SSC)
Dec 14, 2017
- Project Phase A activity officially kicks off Nov. 2017
- Technical scoping work that will feed into the project implementation plan and associated deliverables has been initiated (eg. data inventory, regridding and interpolation algorithms, system architecture design)
- COVERAGE workshop proposal submitted to NASA for consideration by SSC
Aug 28, 2018
- Project Phase A activity is ongoing but approaching completion
- Some of the technical scoping work has been completed (pilot application concepts, data inventory, common gridding/interpolation method). System architecture design activities are progressing but ongoing.
- A COVERAGE workshop activity involving participation of key agency stakeholders/partners has been scheduled as side-meeting at CEOS-SIT-TW Darmstadt. Workshop agenda has been formulated and reviewed by the COVERAGE advisory board, and preparations are underway.
Created:
2017-05-31 13:51:43 UTC
Last Updated:
2021-02-04 03:21:36 UTC